When the customer has accepted the project rental quotation and it is Confirmed, transfer it to a project. The transfer also can create the rental order and order lines. You start the transfer from the project rental quotation.
The transfer takes over the planning from the Advanced WBS:
Project structure: The root project line becomes the main project. Project lines become subprojects, and tasks become activities.
Project forecasts: All estimate lines become project forecasts on their activity: hours, fees, expenses, and items.
Rental items (Order line type = Rental): These estimate lines become rental order lines. Each line refers to the project and activity of its task. Supplementary items and kit structures are kept.
Sales items (Order line type = Sales/purchase): These estimate lines become lines of a separate sales order, linked to the project and activity. If Transfer sales lines to project rental order is set to Yes in the Rental parameters (Finance tab), they become sales lines on the rental order instead.
Prerequisites
The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.
The root project line of the Advanced WBS must have a project contract. Otherwise, the transfer stops with the message “The project contract is not specified.” For more information, see Build Advanced WBS for project rental quotation.
The project rental quotation must have the status Confirmed. For more information, see Mark project rental quotation as Confirmed.
Transfer the quotation
Go to Rental order management > Project rental quotations > Project rental quotations.
In the list, select a project rental quotation with status Confirmed.
On the Action Pane, click Follow up > Transfer to project.
The wizard to transfer the quotation to a project opens.
Click Next.
Select whether to create a new project or to use an existing project.
Options:
New project: The root project line becomes the main project.
Existing project: The projects of the Advanced WBS are added to an existing project. The root project line shows the totals of the whole Advanced WBS. If the project already has a rental order, the rental items are added to it.
Click Next.
In the Project ID field, enter the ID of the new project, or select the existing project.
Click Next.
In the Transfer to project forecast field, select Yes.
All estimate lines of the Advanced WBS are transferred to the project forecasts.
Click Next.
In the Transfer to item requirement/rental order field, select Yes.
The rental items are transferred to the rental order and order lines. The sales items are transferred to a separate sales order, or to the rental order, depending on the Transfer sales lines to project rental order parameter.
Note
If you select No, only the rental project is created. You can create the rental order later from the rental project: On the Projects page, on the Action Pane, click Plan > Transfer from quotation. Select the project quotation lines, and click OK.
Click Next.
Click Finish.
If a message about financial dimensions appears, answer it to decide whether the financial dimensions are transferred.
Note
For more information on the wizard options, see Transfer project quotation to project.
Review the rental project and rental order
On the project rental quotation, review the references to the created project and rental order in the header.
The project rental quotation header shows a reference to the created:
Rental project (General section, Project ID)
Rental order (Reference section, Rental order)
Open the rental order. On a rental order line, in the Line details section, on the Project tab, review the Project ID, Activity number, and Line property.
Each rental order line refers to the subproject and activity of its task. On the rental order header, the Project ID in the Rental project group opens the rental project.
Note
On a project with Use progress billing set to Yes, the rental order lines are not chargeable (Line property NoCharge). For more information, see Invoice rental project and Use progress billing for project rental.
To change the rental project later, see Change rental project and update rental order.
Open the rental project. On the Action Pane, click Plan > Logistics > Project Logistics.
The Project Logistics page shows the orders per project and activity. The rental order is shown as a sales order reference; open it to go to the rental order. If a separate sales order was created for sales items, it is shown as well.