After you transfer the project rental quotation, you can change the rental project in three ways:
With a project change order: Use this when the change needs internal approval or the confirmation of the customer, or when you want the change on record in a change order report.
By editing and publishing the Advanced WBS of the project: Use this for a direct change that needs no approval.
With a new project rental quotation for the existing project: Use this to add new subprojects to the project. You can’t change the existing project or its subprojects. You can only add new subprojects.
With a project change order or the Advanced WBS, new rental items are not added to the rental order automatically. You add them with Transfer from WBS estimates. For more information, see Add new rental items to rental order.
Prerequisite
The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.
Do's and don'ts
These rules apply when you change a rental project with a project change order or the Advanced WBS:
Add each new rental item to the task it belongs to. The rental order line gets the project and activity of that task.
Don’t change rental lines that are already delivered.
Don’t use Stop for rental items in the Advanced WBS. It is not the rental stop, and supplementary items, such as insurance, can’t be stopped this way.
You can change hours, fees, expenses, and sales items as in Project Control Suite.
Note
Changes on the rental order, such as off-rent dates from returns, rental stops, and exchanges, don’t reach the Advanced WBS. Update the Advanced WBS of the project manually.