Build Advanced WBS for project rental quotation

Prev Next

The work breakdown structure (WBS) describes the work to be done for the rental project. You build it in the Advanced WBS of the project rental quotation. You define the project setup, and add subprojects and tasks.

The Advanced WBS has these line types:

  • Root project line: Created automatically for the quotation. When you transfer the quotation to a new project, it becomes the main project.

  • Project line: A subproject under the root project line or another project line. It becomes a subproject when you transfer the quotation.

  • Task: An activity under a project line or another task. You add the estimate lines, such as rental items, to tasks. After the transfer, each rental order line refers to the project and activity of its task.

You can add a task under a task, but you can't add a project line under a task. For more information, see Task types in work breakdown structure.

Prerequisite

The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.

The project rental quotation must be created with Show WBS with units and quantities set to Yes. For more information, see Create project rental quotation with Project Control Suite.

Open the Advanced WBS for editing

  1. Go to Rental order management > Project rental quotations > Project rental quotations.

  2. In the list, select the project rental quotation.

  3. On the Action Pane, click Project quotation > Maintain > Advanced WBS Edit.

    The Work breakdown structure for page opens, ready for editing. Advanced WBS opens the same page read-only, with an Edit button.

    Note

    If Enforce locking for edit is Yes on the quotation, you only see the subprojects that you have locked. Locking works as in Project Control Suite.

Define the project setup

Subprojects inherit the setup of the root project line, unless you override it. So, define the setup of the root project line first.

  1. On the Tasks and estimates tab, select the root project line.

  2. On the Setup tab (lower pane), check that the Project type field is set to Time and material.

    The default comes from the Project Control Suite parameters. A rental project is a time and material project, also when it uses progress billing.

  3. In the Project group field, select the project group.

    The default comes from the Project Control Suite parameters.

  4. In the Project contract ID field, select a project contract. To create a project contract, click the plus button.

    Note

    Define a project contract on the root project line before you transfer the quotation. Otherwise, the transfer stops with the message “The project contract is not specified.”

  5. Set the Use progress billing field.

    The default comes from the Project Control Suite parameters. This setting decides how you invoice the rental project. For more information, see Invoice rental project and Use progress billing for project rental.

    Options:

    • Yes: You invoice with progress bills. The rental order lines are not chargeable.

    • No: You invoice with project invoice proposals. The rental order lines are chargeable.

    For what progress billing needs on the tasks, see Use progress billing.

Add a subproject

Add a subproject for each part of the rental project that you want to manage as a separate project.

  1. Select the root project line, or the project line to add the subproject to.

  2. Click New project.

  3. In the Project name field, enter a name.

  4. To use a different setup for this subproject, set Override to Yes, and fill in the setup fields.

    Without override, the subproject uses the setup of its parent. You can override the Project type, Project group, Project contract ID, Use progress billing, and Subproject ID suffix. The suffix is used to create the subproject ID. A subproject without progress billing is left out of the progress bill.

  5. Click OK.

Add a task

  1. Select the project line or task to add the task to.

  2. Click New task.

  3. In the Task name field, enter a name.

    Note

    Activity templates are not supported with the integration. Leave the Activity template field empty.

  4. In the Category field, select a category.

  5. Fill in the other Task fields as needed.

  6. If you use progress billing, also fill in the Calculation fields like Group and Forecast quantity.

    Note

    In rental, you always rent a discrete quantity of items. Therefor, consider using a calculation group with a variable of type Percentage and 100%.

  7. Click OK.

  8. In the Task start date and Task end date fields, enter the dates of the task.

    The task dates become the default on-rent date and expected off-rent date of the rental items that you add to the task. You can still change the dates per line.

    Note

    • If you change the task dates later, the rental dates of existing lines don't change.

    • Changing the task start and end dates can change the project start and end dates.

    • Group rental items with the same rental period in one task. With Auto scheduling set to No, the dates that you enter are kept.

Note

To change the task hierarchy, you can indent, outdent, or move a task, and change a task to summary or detail. This works as in Project Control Suite. For more information, see Task types in work breakdown structure.