On a rental project with progress billing, you invoice the customer for the progress you report on the project. The posted rental cost and the total rental price per activity help you decide how much to invoice.
Posting the progress bill creates the project invoice proposal. You review the proposal and post it to invoice the customer.
Prerequisites
The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.
Use progress billing must be set to Yes on the project. For more information, see Build Advanced WBS for project rental quotation.
The rental order lines must be delivered, and their costs transferred to the project. For more information, see Transfer Rental order costs.
Review the rental costs on the project
Go to Project management and accounting > Projects > All projects.
In the list, select the rental project.
On the Action Pane, click Plan > Activities > Advanced WBS.
Click the Progress and earned value tab.
Click Refresh.
The rental values are updated with the latest posted transactions.
Review the Total rental price and Posted rental cost per activity.
Posted rental cost comes from the rental transactions posted on the activity. Both values are rolled up to the project lines.
Optionally, click Posted transactions to see the non-chargeable rental transactions.
You can also open them from the project: on the Action Pane, click Manage > Related information > Posted transactions.
Create the progress bill
On the Progress and earned value tab, click Create progress bill.
The Create new progress bill journal dialog opens.
Note
You can also create the progress bill from the project. On the Action Pane, click Manage > Bill > Progress bills, and then click New.
In the Progress bill journal name field, select the journal name.
In the Project ID field, check that the rental project is selected.
In the Invoice date field, enter the invoice date.
Click OK.
Close the Advanced WBS page.
Review the progress bill
Go to the rental project. On the Action Pane, click Manage > Bill > Progress bills.
Click Lines.
On the Journal lines progress bill page, compare the Total rental price and Posted rental cost with the Bid value.
These values help you decide how much progress to invoice for the activity.
Enter the progress in the Progress %, Progress amount, or Current progress quantity field.
The other two fields are calculated.
Click Save.
Note
For Report as finished, Apply progress, certified quantities, retention, and prepayment, see Create progress bill.
Post the progress bill
Go to the rental project. On the Action Pane, click Manage > Bill > Progress bills.
In the list, select the progress bill with workflow status Draft.
Click Post.
Posting creates a chargeable transaction for the progress amount, and the project invoice proposal.
It also updates Earned value in the Advanced WBS and Claimed amount on the progress bill.
Note
Until the project invoice is posted, you can still correct the progress bill. For more information, see Post and close progress bill.
Review the project invoice proposal
Go to the rental project. On the Action Pane, click Manage > Bill > Project invoice proposals.
The invoice proposal for the progress amount has the status Open.
In the list, select the link of the invoice proposal.
On the Invoice proposals page, in the Invoice proposal transactions section, on the On-account tab, review the amount and the activity.
Note
To invoice the customer, post the invoice proposal. For more information, see Post project invoice proposal.
After posting, the invoiced amount shows on the Invoice and margins tab of the Advanced WBS of the project.