Transfer rental order costs

Prev Next

You can transfer rental order costs to the project before posting the invoice. Use Transfer to project on the rental order. This button is only available when Transfer rental order to project is set to Yes in the Rental parameters, on the Finance tab.

This action generates a project hour journal and allocates all rental costs, including insurance, transport, and warranty, based on item categories. You can run it in batch or trigger it manually.

Check the results in: Project > Manage > Posted project transactions.

Rental projects with Project Control Suite

On a project with progress billing, the rental costs reach the project only through Transfer to project. Take the following into account:

  • The rental order lines are not chargeable (Line property with Chargeable set to No). On these rental orders, Invoice and Project invoice proposal are not available.

  • Each delivered rental order line becomes a non-chargeable transaction on the activity of the line. The description shows the rental period. In the Advanced WBS of the project, these transactions show as Posted rental cost. For more information, see Create progress bill for rental project.

  • For the Transfer rental order to project parameter, see Set up Rental Management and Project Control Suite integration.

Steps

  1. Go to Rental order management > Rental orders > All rental orders.

  2. In the list, select the rental order.

  3. On the Action Pane, click Invoice > Generate > Transfer to project.

    The Posting invoice page opens.

  4. In the Quantity field, select an option.

  5. In the Calculation date field, enter the date up to which the rental costs are transferred.

  6. Define the other settings as desired.

  7. Click OK.

    Only delivered rental order lines are transferred. The system posts an hour journal with the description “Transfer to Project from rental order”, followed by the rental order number.