Change rental project by editing and publishing Advanced WBS

Prev Next

You can change a rental project directly in its Advanced WBS. You edit a subproject, add the estimate lines, and publish the changes. Use this for a change that needs no approval.

New rental items keep the project and activity of their task. After you publish, you add them to the rental order. For more information, see Add new rental items to rental order.

Prerequisites

Open the Advanced WBS of the subproject

  1. Go to Rental order management > Rental orders > All rental orders.

  2. In the list, select the rental order of the rental project.

  3. On the header, in the Rental project group, click the Project ID.

    The rental project opens.

    Note

    You can also click the Project ID in the list of rental orders, or open the project from Project management and accounting > Projects > All projects.

  4. On the Action Pane, click Plan > Activities > Advanced WBS.

    The Advanced WBS opens, with the WBS tree on the left.

  5. In the WBS tree, select the subproject that you want to change.

  6. Click Edit.

Open the estimates of a task

  1. On the Tasks and estimates tab, select the task, or click New task to add one.

  2. Check the start date and end date of the task, and change them if needed.

    New rental lines take their on-rent date and expected off-rent date from the task dates. Set the task dates before you add the rental items.

  3. On the lower pane, on the Estimated costs and revenues tab, click New.

Add a rental item

  1. In the Transaction type field, select Item.

  2. In the Rental transaction type field, select Rental.

  3. In the Item number field, select a rental item.

    The Order line type is set from the item and shows Rental.

  4. In the Quantity field, enter the quantity.

  5. On the Rental tab, review the rental fields, such as the rate code, rental type, transport, and insurance. Change them if needed.

    The tab works as on a rental order line.

  6. On the Rental dates tab, review the on-rent date and expected off-rent date.

    The dates default from the task start date and task end date. You can change them on this tab or in the grid. When you change a date, the total rental price is recalculated.

    Note

    Some dates only show when their configuration key is enabled.

  7. Click Save.

    The rental price is calculated from the rental agreement. For a kit or an item with supplementary items, the Rental Line Editor opens. Add the supplementary items and kit components. They are added as separate lines that refer to the main line.

    Note

    • You can delete the main line, but not a supplementary line on its own.

    • To change the supplementary items later, click Edit rental lines.

  8. Under Rental agreements, select the header or line rental agreement.

    Each estimate line can use a different rental agreement. The quotation itself has no rental agreement.

    Note

    Line agreements are not available until the estimate line exists.

  9. Review the line.

Note

Publish the Advanced WBS

  1. Optionally, click Rental totals to review the rental amounts.

    The Rental invoice details page opens.

  2. Click Publish.

    The WBS calculation runs, and the Advanced WBS and the project forecasts get the new lines.

    Note