Add new rental items to rental order

Prev Next

When you transfer the project rental quotation, its rental items become rental order lines automatically. Rental items that you add later, with a project change order or by editing and publishing the Advanced WBS, don’t. You add them to the rental order of the project with Transfer from WBS estimates.

Each new rental order line gets the project and activity of its task.

Prerequisites

Transfer the new rental items

  1. Go to Rental order management > Rental orders > All rental orders.

  2. In the list, select the rental order of the rental project.

  3. On the header, in the Rental project group, click the Project ID.

    The rental project opens.

    Note

    You can also click the Project ID in the list of rental orders, or open the project from Project management and accounting > Projects > All projects.

  4. In the Project hierarchy section, select the subproject that has the new rental items.

    Note

    Run the transfer on the subproject. On the main project, the dialog shows no lines.

  5. On the Action Pane, click Plan > Item requirements > Transfer from WBS estimates.

    The Transfer WBS item estimates dialog opens.

  6. Optionally, in the Activity number field, select the activity of the new rental items.

  7. Select the new rental items.

    Select only the lines that are not on the rental order yet.

  8. Click OK.

    The rental order gets a new line for each selected rental item, with the project and activity of its task.

Review the rental order lines

  1. On the subproject, on the Action Pane, click Plan > Logistics > Project Logistics.

    The page shows the rental order per activity.

  2. Optionally, on the rental order, select a new line. In the Line details section, on the Project tab, review the project, activity number, and line property.