With the STAEDEAN Rental Management and Project Control Suite integration, you can manage complex project structures for long period rentals. The Advanced WBS capabilities of Project Control Suite are integrated into the project rental quotations. STAEDEAN Rental Management is the front end for the whole process. You work from the project rental quotation, the rental order, and the rental project.
Prerequisite
The integration must be set up before you can use it. For the required licenses, configuration key, and setup, see Set up Rental Management and Project Control Suite integration.
Flow diagram
When to use the integration
Use a project rental quotation with Project Control Suite when you want to plan a rental project in detail, with a project structure, tasks, quantities, and margins.
The standard project rental quotation flow remains available and unchanged. Use it for quotations that don't need the Advanced WBS. For more information, see Project rental quotation.
Note
Only new project rental quotations can be planned in the Advanced WBS. You decide this when you create the quotation, and you cannot change it afterwards.
How you bill a rental project
A rental project is a time and material project. The Use progress billing setting on the project decides how you bill it:
Without progress billing: The rental order lines are chargeable. You bill them with project invoice proposals.
With progress billing: The rental order lines are not chargeable. The rental costs are posted to the project, and you bill the progress with progress bills.
For more information, see Bill rental project and Use progress billing for project rental.
What is synchronized between the Advanced WBS and the rental order
When you transfer the quotation, the rental items in the Advanced WBS become rental order lines. Each line keeps its subproject and activity, and the rental dates from the Advanced WBS.
After the transfer, you change the Advanced WBS of the project through a project change order or by editing and publishing it. New rental items don't reach the rental order automatically: you add them with Transfer from WBS estimates on the project. For more information, see Change rental project and update rental order.
Changes on the rental order, such as off-rent dates from returns, a rental stop, or an exchange, don't reach the Advanced WBS. The project leader updates the Advanced WBS manually.
Unsupported Project Control Suite functionality
The following Project Control Suite functionality is not supported in the integration:
Subcontracting of rental items
Additional costs and indirect costs
Consumption-based billing
Project inventory
WBS cost control
WBS templates
Activity templates
Copy to new quotation
Export and Import of the Advanced WBS
Fixed-price rental projects
Stop for rental items in a project change order
Synchronization with Customer Engagement