With the STAEDEAN Rental Management and Project Control Suite integration, you plan a project rental quotation in the Advanced WBS. To do so, you create the quotation with Show WBS with units and quantities set to Yes.
You can only set this field when you create the quotation. The other Project Control Suite settings are on the quotation header. You can change them later.
Prerequisite
The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.
Create the quotation
Go to Rental order management > Project rental quotations > Project rental quotations.
Click New.
The Create project rental quotation dialog opens.
In the Account type field, select Customer or Prospect.
In the Customer account field, select the customer.
When you are asked Transfer customer information?, select an option.
The settings of the customer are copied to the quotation, such as the contact, address, invoice profile, rental calendar, and rate code.
Options:
Yes: The settings are copied. You can still change them.
No: The settings stay empty and you must enter these manually, at least the mandatory ones.
In the Customer section, review the defaulted fields, such as Contact, Delivery address, and Project ID. Change them if needed.
In the Show WBS with units and quantities field, select Yes.
You find the field in the Forecast quantities and scheduled units group, at the bottom of the Customer section. The default comes from the Project Control Suite parameters.
Options:
Yes: You plan the quotation in the Advanced WBS and generate the quotation lines from the Advanced WBS.
No: You use the standard project rental quotation. For more information, see Create and send project rental quotation.
Note
You can only change this field in this dialog. After you click OK, the field is read-only.
In the Rental section, review the defaulted fields, such as Invoice profile, Rental calendar, Rate code, and the estimated dates. Change them if needed.
In the Rental dates section, review the dates and change them as needed.
Note
If you have set the Estimated project end date, that is the default Expected off-rent date. If not, the Expected off-rent date is the only required date to fill in.
The other dates default to today.
Click OK.
The project rental quotation is created with the status Created. On the Action Pane, under Project quotation > Maintain, Advanced WBS and Advanced WBS Edit are now available.
Set the Project Control Suite settings
The Project Control Suite settings of the quotation are in the Project control suite section. You can only change them when Show WBS with units and quantities is Yes.
Go to Rental order management > Project rental quotations > Project rental quotations.
In the list, open the project rental quotation.
On the Header tab, expand the Project control suite section.
In the Enforce locking for edit field, select an option.
Locking works as in Project Control Suite.
Options:
Yes: Advanced WBS Edit only shows the subprojects that you have locked.
No: All subprojects are shown.
In the Auto scheduling field, select an option.
The default comes from the Project Control Suite parameters. You can change this setting at any time.
Options:
No: The task dates that you enter are kept. This is recommended, because rental items in one task often need different end dates.
Yes: The task dates are scheduled automatically.
If you prepare the Advanced WBS in Excel, set Generate WBS ID to Yes.
The WBS IDs of the lines that you add in Excel are generated when you publish from Excel. For more information, see Edit Advanced WBS in Excel with rental fields.
Click Save.