Multiple capabilities can be added to a resource. This is an optional setup.
Capabilities can be setup on a task (under Task requirements). This can allow a validation when assigning the task to a resource from a plan board, whether the resource holds that capability to complete the task.
| 1. | Go to Work order project planning > Resources > Resources. |
| 2. | In the list, find and select the desired resource. |
| 3. | Click Add. |
| 4. | In the Capability field, enter or select a value. |
| 5. | In the Expiration field, enter a date. |
| 6. | Click Save. |