Resource calendars are optional. You can set up calendars to define the working times for a resource.

You can enter an expiration date for each calendar. To view expired calendars:

  • Open the View drop-down menu
  • Select All


Standard procedure

1. Go to Work order project planning > Resources > Resources.
2. In the list, find and select the desired resource.
3. Click Add.
4. In the Calendar field, enter or select a value.
5. In the Expiration field, enter a date and time.
6. Click Save.