Before you process the project rental quotation, review its totals and margin in the Advanced WBS. This works as in Project Control Suite, but the totals include the rental prices of the rental items.

The bid value of the quotation is the sum of:

  • The sales prices of all estimate lines, such as sales items, hours, fees, and expenses.

  • The Total rental price of all rental item lines.

The rental prices themselves are calculated from the rental agreements, in the same way as on a rental order or rental quotation. They always match the amounts in Rental totals.

Prerequisite

The STAEDEAN Rental Management and Project Control Suite integration must be set up. For more information, see Set up Rental Management and Project Control Suite integration.

The Advanced WBS must have its estimated costs and revenues. For more information, see Enter estimated costs and revenues for project rental quotation.

Update the totals

  1. Go to Rental order management > Project rental quotations > Project rental quotations.

  2. In the list, select the project rental quotation.

  3. On the Action Pane, click Project quotation > Maintain > Advanced WBS Edit.

  4. If an exclamation mark shows on a task or project line, click Run WBS calculation.

    The WBS calculation rolls up the totals, including the rental prices. It doesn't recalculate the rental prices themselves. For more information, see Run WBS calculation for project rental quotation.

Review the rental totals

Rental totals opens the Rental invoice details page. It shows the rental, consumption, transport, and cost amounts.

  1. If it isn't open yet, open the Advanced WBS of the quotation with Advanced WBS Edit.

  2. To review the rental totals of one rental item, on the Estimated costs and revenues tab, select the rental item line. Then, on the Action Pane, click Rental totals.

    Note

    Rental totals is only available on lines with Rental transaction type = Rental and Order line type = Rental.

  3. To review the rental totals of the whole quotation, on the Action Pane, click Rental totals.

  4. Close the Rental invoice details page.

Review cost and revenue

  1. If it isn't open yet, open the Advanced WBS of the quotation with Advanced WBS Edit.

  2. On the Tasks and estimates tab, select a task or project line.

  3. Click the Cost and revenue tab.

    Next to the Project Control Suite columns, the tab shows the Total rental cost price and Total rental price of the rental items.

Review the bid value

  1. If it isn't open yet, open the Advanced WBS of the quotation with Advanced WBS Edit.

  2. On the Tasks and estimates tab, select a task.

  3. Click the Calculation tab (lower pane), and review the Bid value and Bid rate.

    The calculated value includes the Total rental price of the rental items on the task. You can change the bid value and bid rate as in Project Control Suite. For more information, see Review bid rate and bid value.

Note

You can also use calculations in the Advanced WBS. For more information, see Use calculations in work breakdown structure.

Review the margin by cost code

This is optional. Use it if you use cost codes in the Advanced WBS. For more information, see Use cost codes in work breakdown structure.

  1. If it isn't open yet, open the Advanced WBS of the quotation with Advanced WBS Edit.

  2. On the Tasks and estimates tab, select the root project line.

    On the root project line, you see the totals of the whole Advanced WBS.

  3. Click the Cost codes tab.

  4. In the Revenue field, select Yes.

  5. In the Cost field, select Yes.

  6. Click Refresh.

    The cost value, bid value, and margin are shown by cost code. The Total rental cost price column shows the cost of the rental items. For more information, see Review cost value, bid value, and margin by cost code.

Simulate a sales price with margin or markup

This is optional. On the Quotation statement page, you can simulate a suggested sales price for a project line, based on a margin or markup percentage:

  • Margin %: (Sales price - Cost price) / Sales price × 100%.

  • Markup %: (Sales price - Cost price) / Cost price × 100%.

  1. Click Quotation statement.

  2. Simulate the sales price, and transfer it to the contract total if needed.

    This works as in Project Control Suite. For more information, see Define project quotation contract totals.

    Note

    You can only transfer the suggested sales price to fixed-price project lines without progress billing. For a rental project with progress billing, use the simulation for review only.