Enter the start and end date/time in the Synchronization mode if Initialize only or Keep synchronized is selected.

This setup determines the date and time on work order lines. Set values for each task individually.

You can base the start/end date on:

  • Session date: Uses the system date.
  • Rental date: Uses the date from the linked rental order.
  • Template line: Uses the selected template line.
  • Work order date: Uses the creation date of the work order.
  • Delivery date: Uses the delivery date.

You can base the start/end time on:

  • Session date: Uses the system date.
  • Rental date: Uses the date from the linked rental order.
  • Template line: Uses the selected template line.
  • Fixed: Enter the time manually.

You can also add offset values based on units such as days, weeks, months, or years.


Standard procedure

1. Go to Work order project planning > Setup > Work order template.
2. In the list, find and select the desired record.
3. Click Edit.
4. In the Start date field, select an option.
5. In the Start time field, select an option.
6. In the End date field, select an option.
7. In the End time field, select an option.
8. In the Offset fields, enter values. (Optional)
9. Click Save.

Provide feedback