You can configure several fields in the task setup under the Setup tab. Select a task category:
Additional setup options:
You can assign a work order line to a resource in the following ways:
| 1. | Go to Work order project planning > Setup > Tasks. |
| 2. | In the list, find and select the desired task. |
| 3. | In the Task category field, select an option. |
| 4. | In the Task group field, enter or select a value. |
| 5. | In the Object not available status field, select an option. |
|   |
Note: If a Business object availability change of status is not required skip the step. |
| 6. | In the Object available status field, select an option. |
|   |
Note: If a Business object availability change of status is not required skip the step. |
| 7. | Select Yes in the Object assignment via service plan board field. |
|   |
Note: If a Business object assignment via Service Plan Board or Transport Plan Board is not required skip the step. |
| 8. | Select Yes in the Auto schedule linked resources field. |
|   |
Note: If auto-schedule of linked resources is not required skip the step. |
| 9. | Select Yes in the Resource required field. |
|   |
Note: If resources are not required skip the step. |
| 10. | Select Yes in the Synchronize quantity field. |
|   |
Note: If quantity synchronization is not required skip the step. |
| 11. | Select Yes in the Auto generate hour journal field. |
|   |
Note: If Auto generate of hour journal is not required skip the step. |
| 12. | Click Save. |
| Related to | Notes |
|---|---|
|
Create and maintain tasks |
  |