The requested start and end date/time on the work order template populate automatically based on the synchronization mode defined in the template.
If no synchronization mode is set, these fields remain blank, and the task will not appear on the plan board for scheduling.
In that case, manually enter the requested start and end date/time on each task line in the work order.
| 1. | Go to Work order project planning > Work orders > All work orders. |
| 2. | In the list, click the link for the selected work order. |
| 3. | Click Edit. |
| 4. | In the list, mark the selected row. |
| 5. | In the Requested start date/time field, enter a date and time. |
| 6. | In the Requested end date/time field, enter a date and time. |
| 7. | Click Save. |
| Related to | Notes |
|---|---|
|
Execute work order tasks (F&SCM) |
  |