A work order status can be updated from the work order task line on the work order. Go to the work order > Task line > Update line tab. A task status can also be updated on the plan board after the task has been scheduled to a resource.
| 1. | Go to Work order project planning > Work orders > All work orders. |
| 2. | In the list, click the link to the selected work order. |
| 3. | Click Update line on the work order line tab. |
| 4. | Choose a status to update the work order to |
| 5. | Click Save. |