The Production orders section displays production orders affected by the selected ECO line.
A production order might continue to use the previous BOM or route after an engineering change. Use the available actions to:
The actions available for an order depend on its production status.
Prerequisites
Before you begin, make sure that:
The impact calculation is complete.
The affected order appears in the Production orders section.
You have permission to manage production orders.
The production order has a status supported by the selected action.
The new BOM or route version is active, where applicable
Action availability
The actions available in the Production orders section depend on the current production order status. The following table shows when each corrective action is available.
Action | Estimated | Released | Started | Reported as finished | Ended |
|---|---|---|---|---|---|
Update BOM | Available | Unavailable | Unavailable | Unavailable | Unavailable |
Update route | Available | Unavailable | Unavailable | Unavailable | Unavailable |
Estimate | Available | Available | Available | Unavailable | Unavailable |
Hold | Available | Available | Available | Available | Unavailable |
Note
When a production order is on hold, all other corrective actions are unavailable. Select Unhold before performing another action.
Update BOM is unavailable if the ECO line doesn’t contain a BOM change. Update route is unavailable if the ECO line doesn’t contain a route change.