Manage production order - Impact workspace

Prev Next

The Production orders section displays production orders affected by the selected ECO line.

A production order might continue to use the previous BOM or route after an engineering change. Use the available actions to:

The actions available for an order depend on its production status.

Prerequisites

Before you begin, make sure that:

  • The impact calculation is complete.

  • The affected order appears in the Production orders section.

  • You have permission to manage production orders.

  • The production order has a status supported by the selected action.

  • The new BOM or route version is active, where applicable

Action availability

The actions available in the Production orders section depend on the current production order status. The following table shows when each corrective action is available.

Action

Estimated

Released

Started

Reported as finished

Ended

Update BOM

Available

Unavailable

Unavailable

Unavailable

Unavailable

Update route

Available

Unavailable

Unavailable

Unavailable

Unavailable

Estimate

Available

Available

Available

Unavailable

Unavailable

Hold

Available

Available

Available

Available

Unavailable

Note

  • When a production order is on hold, all other corrective actions are unavailable. Select Unhold before performing another action.