You can use project inventory tracking to make sure that project-specific inventory is only used by the project to which it is assigned.
Project inventory ensures a direct relation between demand lines and coverage unlike regular master planning which is done anonymous.
To track project inventory, you use project inventory numbers on projects and tracking dimension groups on products:
As a result, you can track project inventory for the products with a tracking dimension group for which the Project inventory number dimension is active.
If there is demand for a project, for example an item requirement, with a project inventory number defined, this demand can be fulfilled with on hand inventory:
If you have project demand for a BOM product, and project inventory is tracked, the project inventory number is applied to all levels of the BOM.
However, if for a product on a BOM line no project inventory tracking is active, the project inventory number is not applied to this product, and also not to BOM levels beneath this product.
If you run the master plan for demand for the same product but with different project inventory numbers defined, a separate planned order is created for each project inventory number.
If you have project-specific demand, for example an item requirement with a project inventory number defined, and:
If you have, for a project, several project-specific item requirement lines with the same item, one planned order is created for these requirements.
Name | Responsible | Description |
---|---|---|
Assign project inventory tracking dimension group to product |
Project manager |
Assign a tracking dimension group, with the Project dimension active, to the products for which you want to track project inventory. |
Assign project inventory number to project |
Project manager |
If you want to track project inventory for a project, you must assign a project inventory number to the project. As a result, you can track project inventory for the products with a tracking dimension group for which the Project dimension is active. |
Remove project inventory number from project |
Project manager |
You can remove a project inventory number on a project. This is only applied to new transactions for the project. Existing transactions aren't changed. |
Name | Responsible | Description |
---|---|---|
Assign project inventory tracking dimension group to product |
Project manager |
Assign a tracking dimension group, with the Project dimension active, to the products for which you want to track project inventory. |
Assign project inventory number to project |
Project manager |
If you want to track project inventory for a project, you must assign a project inventory number to the project. As a result, you can track project inventory for the products with a tracking dimension group for which the Project dimension is active. |
Remove project inventory number from project |
Project manager |
You can remove a project inventory number on a project. This is only applied to new transactions for the project. Existing transactions aren't changed. |
Related to | Notes |
---|---|
Use project inventory |
  |