When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS.
You can update these changes to the integration journal to keep the bid rates and bid values intact.
Name | Responsible | Description |
---|---|---|
Review bid rate and bid value |
Project manager |
WBS calculation updates the bid rate and bid value for each task. The relevant calculations are:
You can manually change the bid rate and bid value. If you do so, these are automatically locked. If the bid rate and bid value are locked and you run the WBS calculation:
You can unlock the bid rate. To do so, on the Advanced WBS page, on the calculation fast tab, clear the Lock bid rate check box. |
Update integration journal |
Project manager |
When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS. You can update these changes to the integration journal to keep the bid rates and bid values intact. |
Name | Responsible | Description |
---|---|---|
Review bid rate and bid value |
Project manager |
WBS calculation updates the bid rate and bid value for each task. The relevant calculations are:
You can manually change the bid rate and bid value. If you do so, these are automatically locked. If the bid rate and bid value are locked and you run the WBS calculation:
You can unlock the bid rate. To do so, on the Advanced WBS page, on the calculation fast tab, clear the Lock bid rate check box. |
Update integration journal |
Project manager |
When the integration journal is published to the advanced WBS, you can change the bid values and bid rates in the advanced WBS. You can update these changes to the integration journal to keep the bid rates and bid values intact. |
Related to | Notes |
---|---|
Update integration journal |
  |