If you have finished the project changes on a project change order, including the estimates and pricing setup, you must submit the project change order for review. A project change order must be approved internally before you can send it to the customer or transfer it to the project.
1. | Click Project management and accounting -> Common -> Change orders -> Project change orders. |
2. | On the Project change orders form, select a project change order. |
3. | Double-click or press Enter on the selected project change order. |
4. | On the Project change orders form, click Submit |
5. | On the dialog, enter a comment and click Submit. |
6. | Close the Project change orders form. |
Related to | Notes |
---|---|
Create and manage project change orders |
  |