Review purchase order

Prev Next

As the assigned reviewer, review the purchase order.

To finish the review, choose one of these options:

  • Approve: The purchase order is approved.

  • Reject: The purchase order is rejected. The purchase order must be adjusted or cancelled.

  • Request change: A change is required. The purchase order is re-assigned to the submitter.

  • Delegate: The review is delegated to another user defined in the workflow.

Steps

  1. Go to Project management and accounting > Projects > All projects.

  2. Click New.

  3. In the Project type field, select an option.

  4. In the Project name field, type a value.

  5. In the Project group field, enter or select a value.

  6. In the Project contract ID field, enter or select a value.

  7. In the Project manager field, enter or select a value.

  8. In the Start date field, enter a date.

  9. Click Create project.

  10. In the Actual start date field, enter a date.

  11. In the Projected end date field, enter a date.

  12. Click Save.

  13. Close the page.