If you finished the setup of a test run, and the test must be done, change the test run status to Scheduled. As a result, the test run can be started by the tester.


Standard procedure

1. Click Business process testing.
2. Click the Test runs tab.
3. In the list, mark the selected row.
4. Click Status.
5. Click Scheduled.
6. Close the page.