Cost resources in production

Prev Next

When resources are linked to capacity centers, the costs of that capacity center are assumed to include the resource cost:

  • As part of the Direct Unit Cost, or

  • As part of the Indirect Cost %, or

  • As part of the Overhead Rate.

The actual resource time is recorded as a resource ledger entry.