You can edit project forecasts and then generate indirect costs. As an example, in this topic, the hours forecast is edited.
| 1. | Go to Project management and accounting > Projects > All projects. |
| 2. | In the list, find and select the project. |
| 3. | On the Action Pane, click Plan. |
| 4. | Click Hour forecasts. |
| 5. | Click New. |
| 6. | In the list, mark the selected forecast line. |
| 7. | In the Category field, enter or select a value. |
| 8. | In the Hours field, enter a number. |
| 9. | Click the Financial dimensions tab. |
| 10. | In the Department value field, enter or select a value. |
| 11. | Click the Overview tab. |
| 12. | Click the Indirect costs tab. |
| 13. | Click Save. |
| Related to | Notes |
|---|---|
|
Manage project forecasts |
  |