You can set up projects manually in several ways. The default indirect cost plan comes from the project contract. On a project, you can change it.
1. | Go to Project management and accounting > Projects > All projects. |
2. | Click New. |
3. | In the Project name field, type a value. |
4. | In the Project group field, enter or select a value. |
5. | In the Project contract ID field, enter or select a value. |
6. | In the Start date field, enter a date. |
7. | In the Project manager field, enter or select a value. |
8. | Click Create project. |
9. | Expand the Government contracting section. |
10. | In the Customer PO number field, you can assign the customer's PO number to this project. |
11. | Select Yes if your project is CAS covered. |
12. | In the CLIN ID field, you can enter information as needed. |
13. | In the Prime contract number field, you can enter the prime contract number from your contract. |
14. | In the Subcontract number field, you can enter your information as needed. |
15. | On the Action Pane, click Plan. |
16. | Click Indirect cost plan. |
17. | Click Modify Indirect Cost Plan to open the drop dialog. |
18. | In the Indirect cost plan field, enter or select a value. |
19. | Click OK. |
20. | Click Yes. |
21. | Click Save. |
22. | Close the page. |