--- title: "Set up subcontract management" slug: "set-up-subcontract-management" tags: ["Flow", "Project Control Suite", "PCS"] status: "new" updated: 2026-03-20T08:30:35Z published: 2026-03-20T17:46:07Z canonical: "docs.staedean.com/set-up-subcontract-management" --- > ## Documentation Index > Fetch the complete documentation index at: https://docs.staedean.com/llms.txt > Use this file to discover all available pages before exploring further. # Set up subcontract management In construction business, it's common to: - Subcontract subprojects or activities to another company, which does the work you. If you subcontract a subproject or activity, you purchase a service from a vendor. This service usually includes a combination of labor, equipment, and materials. - Hire external persons to do (a part of) the work for you. If you hire an external worker, you purchase a service from a vendor. This service usually includes only labor. ## Flow diagram [Embedded content](https://viewer.diagrams.net/?tags=%7B%7D&lightbox=1&highlight=0000ff&edit=_blank&layers=1&nav=1&title=Set_up_subcontract_management.drawio&dark=auto#R%3Cmxfile%3E%3Cdiagram%20name%3D%22Set%20up%20subcontract%20management%22%20id%3D%22diagram4%22%3E7ZnfU9s4EMf%2FmsyUhzCx5Rh4hAC9h94cM5kbrvemWGtbRbY8spwf%2FetvZcvxL2idNlAyV3jAu9qVnO9%2BvJLJhCyS7UdFs%2FhPyUBM3BnbTsjtxHUdz%2FXxj%2FHsKs%2BV71SOSHFmgxrHkn8F65xZb8EZ5J1ALaXQPOs6A5mmEOiOjyolN92wUIruqhmNYOBYBlQMvY%2Bc6dh6Hf%2BqGfgDeBTXS%2FtzrxpJaB1tP0oeUyY3LRe5m5CFklJXV8l2AcKoVwtT5d2%2FMLq%2FMwWpHpMQF4%2BzR%2FUQXW%2FXO%2Fd6vf73K5tPn5nFunK9q0XAeVBvNG42MdewzGhgRjZYcvTFOhFoOXgZciEWUkhV5pEwDN0gQH%2BulXyC1sis%2FNmP1NLapddUFHbppaZKWy8oDdvWPdqP%2BRFkAlrtMCRuVcKzsm%2BasvnWZSchxNq7bga1zET7iRtV8cIKW5p%2F56D%2BWn0x5LkzQVcg7G2DcRSZ0bFYIZxa0TImoSkSkxixS9UprgAqrxYWPH2q8s0yNC1CTCoUTyO0mQww7D4HPS2yaWvWaTPntJnxpQjMN7flfg8Mt6WwBenbkChZpAyYJeEwUFYzIOD%2FACiHIXE5RMLpMbGPsUw47uFQoNni4oCHkYx5GPtCdHTFHpOZuGQbmX58Hgq5CWJ8hM4ZBDznMsWgktMHmXNd2rcBrgao942Rk2Pv%2B9QLWEmtZYIBVPDo2YxrO6Bl1quuMPJPGVVPH8qOAD52BBc1Ql0JMPN7himDB%2F%2B%2BKPVqUVw%2BBridEMfwIEMc%2FYDDZ9NMSaN03h5VpvRcQbU1lPkSHzNyf6xe4vV6idfl5vWbify5roHpU0PHiFbgvWUrYBQuw%2BGe0cXIdoUao3lwcUXJ2aBLuK%2FVJXpNghynSYyo%2F88Uf5D7zaLPfxe9V3Tvdao%2Bbmvw39U5rda4add3KXurU9rl4bKP0%2FiimhfY4JVgKLosVADfP1e3i4PTLq0plY5lJFMq7hrvTfcJamI%2BSbOrls4voPXOviXRQstuWfEu1e4fNGbn89r8bMzauN12rF1tbblupaH1uZ4Rr5skY9Q5409qZjV2bd7FzMlB0DznwX7Hx%2BN9BHrkObTFkAJBNV93C3V0Ii6PSIR7UkQY6wEUL18mTgAT8isxuToiJuSkMKmJaPHQ0PE8Ecbok%2FVWlHiDfWvZe78YDZHdnWbnvu9fvMyVne1B8vKNvw6RYZiDHoC3X%2FTHWaz%2Fcfb%2FhdE5ERjnAxgX3RP6qZPoHJFE7xRJfI8bpf8rN0rHPSIS899IvGsk0Gy%2B3KiaSvMdEbn7Dw%3D%3D%3C%2Fdiagram%3E%3C%2Fmxfile%3E) ## Related - [Set up subcontract management parameters](/set-up-subcontract-management-parameters.md)