Set up progress amount retention terms

Prev Next

If you use retention terms that are based on an invoiced amounts schedule, set up the progress amount retention terms.

Example

Retention schedule:

Amount from

Amount to

Retention percentage

0

500,000

8

500,000

800,000

6

800,000

9,999,999

4

Retention calculation:

Progress bill amount

Total claimed amount*

Retention calculation

Retention

1

400,000

0

400,000 x 8%

32,000

2

200,000

400,000

(100,000 x 8%) + (100,000 x 6%)

14,000

3

100,000

600,000

100,000 x 6%

6,000

4

300,000

700,000

(100,000 X 6%) + (200,000 x 4%)

14,000

*Total claimed mount = The sum of the previous progress bill amounts.

Steps

  1. Click Project management and accounting -> Setup -> Retention -> Progress amount retention terms.

  2. Click New and enter a description.

  3. On the Schedule pane, click Add line and fill in the fields.

    Note

    You only can fill in the Amount to and the Percent to retain. The Amount from is automatically determined based on the highest entered To amount.