Run WBS calculation

Prev Next

If the setup of the work breakdown structure or a part of it is complete, run the WBS calculation.

As a result, based on the calculation setup, this data is calculated.

  • Estimate line quantities if impacted by formulas or variables.

  • Totals for both cost values and sales values.

  • Rates.

Steps

  1. Click Advanced project management.

  2. Click Project quotation.

  3. In the list, click the link in the selected row.

  4. Click Advanced WBS.

  5. Click Edit.

  6. Click Run WBS Calculation.