New or changed features in Release 10.0.49.66 (October 2026) - Project Control Suite (PCS).
Version information:
Product | Version | Minimum version | Latest validated version | Planned next |
|---|---|---|---|---|
Project Control Suite | 10.0.49.66 | D365 F&SCM 10.0.48 | D365 F&SCM 10.0.49 | On demand |
What’s new
New or changed features in Release 10.0.49.66 (October 2025) - Project Control Suite (PCS).
1. Project inventory dimension on document routing label layouts
The Project inventory dimension is now available as a field in document routing label layouts. Before this release, you could print standard inventory dimensions such as site, warehouse, batch number, and serial number. The project dimension was missing from the layout field list. You can now print the project reference on product labels, shipping labels, and license plate labels.
All label types use the same document routing layout. The D365 F&SCM web client and the Warehouse Management mobile app also use this layout. So, the project dimension is available on every label type and print channel.
Key capabilities:
Add the Project inventory dimension to a label layout on the Document routing layout page. Use the standard ‘FieldName’ placeholder syntax in the ZPL definition.
Print the project dimension on product labels during material registration, from the Batches and Sub batches pages, and at manufacturing order start.
Print the project dimension on shipping labels when you close a container or reprint them from the Containers page.
Print the project dimension on license plate labels from the License plates page, during purchase order receipt, and during work execution on the mobile device.
Keep existing label layouts unchanged. Layouts that do not reference the project dimension work as before.
Note
The label layout data source must include the inventory dimensions table. Transactions without a project inventory reference print a blank value for the project dimension.
The label layout data source must include the inventory dimensions table. Transactions without a project inventory reference print a blank value for the project dimension.
2. Open in Excel on the Advanced WBS pages
The Open in Excel function on the Advanced WBS pages now works consistently. Before this release, the button on the committed view of a project quotation did nothing. The committed view and the edit view also showed a different set of Excel templates.
Key capabilities:
Open the WBS of a project quotation in Excel from both the Advanced WBS page and the Advanced WBS edit page.
Select from the same relevant Excel templates on both project quotation pages.
Open the WBS of a project in Excel from the Advanced WBS edit page. The Open in Excel button is no longer shown on the committed Advanced WBS page for projects.
See also: Open the WBS in Excel from the Advanced WBS
3. WBS ID generation for project nodes imported from Excel
WBS ID generation for project nodes imported through Excel integration is improved. Before this release, the system created project nodes at the same level as nested projects, one under the other. The system now assigns each project node its own WBS ID, based on its position in the Excel structure.
Key capabilities:
Create several project nodes at the same level in Excel. Each node gets a separate WBS ID when you publish.
Keep activities nested under their parent project node, like before.
Build the full WBS of a project quotation in Excel with the Generate WBS ID parameter turned on in the Project Control Suite section of the quotation header.
See also: Generate WBS IDs when you publish the WBS from Excel
Bug fixes
Bug fixes in Release 10.0.49.66 (October 2026) - Project Control Suite (PCS).
Bug ID | Title | Description |
|---|---|---|
235030 (CS00239028) | Project invoice proposals generate error after 10.0.45 upgrade | After upgrading to version 10.0.45, opening any invoice proposal from the Project invoices page triggered an "Object reference not set to an instance of an object" error. The Header and Lines view feature, enabled by default in 10.0.45, caused this error. |
230949 (CS00238196) | Customer retention amount calculated incorrectly with sub-projects | When creating an invoice proposal for a project with sub-projects, the system multiplied the retention amount by the number of sub-projects instead of applying it once. |