Allocate budget using cost codes on Advanced WBS
- Updated on Mar 20, 2026
- Published on Feb 13, 2026
Prev Next You can use the 'Advanced WBS' to allocate budget to a project using cost codes.
Steps
Click Advanced project management.
In the list, find and select the desired record.
Click Advanced WBS.
Click the Budget allocation tab.
Click Allocate budget.
Click Refresh.
Close the page.
Was this article helpful?