--- title: "Add contingency" slug: "add-contingency" tags: ["Task", "Project Control Suite", "PCS"] updated: 2026-03-20T08:38:38Z published: 2026-03-20T17:46:03Z canonical: "docs.staedean.com/add-contingency" --- > ## Documentation Index > Fetch the complete documentation index at: https://docs.staedean.com/llms.txt > Use this file to discover all available pages before exploring further. # Add contingency To each task, you can add a contingency. A contingency is an additional value on top of the calculated value, without adding an extra estimate line to a task. You can also use the contingency to, for example, add a risk or a margin. The relevant calculations are: - Bid value = Calculated value + Contingency + Index - Calculated value = sum of Total sales prices of all estimate lines for the task. ### Steps 1. Click **Advanced project management**. 2. Click **Project quotation**. 3. In the list, click the link in the selected row. 4. Click **Advanced WBS**. 5. Click **Edit**. 6. In the list, find and select the desired task. 7. Click the **Calculation** tab. 8. In the **Contingency** field, enter a number. 9. Click **Save**. > [!NOTE] > **Notes** > > - If you add or change a contingency, the bid rate and bid value are not locked automatically. > - A contingency is considered if the bid rate and bid value are unlocked when you add the contingency. ## Related - [Review bid value and markup](/review-bid-value-and-markup.md)