You can post a negative progress bill journal to report any negative progress on an activity or a complete project after the invoice is posted.
You can use this to report the correct progress when you have posted a higher progress than the percentage of completion times the contract value.
Standard procedure
| 1. |
Go to Project management and accounting > Journals > Progress bill > Project. |
| 2. |
Click New. |
| 3. |
In the Progress bill journal name field, enter or select a value. |
| 4. |
In the Project ID field, enter or select a value. |
| 5. |
In the Invoice date field, enter a date. |
| 6. |
Click OK. |
| 7. |
In the From date field, enter a date. |
| 8. |
In the To date field, enter a date. |
| 9. |
In the list, find and select the desired record. |
| 10. |
In the Current progress quantity field, enter a number. |
| 11. |
You can enter a negative progress quantity, progress amount, or progress percentage. In these steps, you enter a negative progress percentage. |
|   |
In the Progress % field, enter a number. |
| 12. |
Close the page. |
| 13. |
Click Post. |
| 14. |
Click OK. |
| 15. |
Close the page. |