If a progress bill is approved by the customer, you can post and close the progress bill. As a result, an invoice journal is created for the project. For each invoiced sub-project, a separate on-account line is added to the invoice journal.
| 1. | Go to Project management and accounting > Journals > Progress bill > Project. |
| 2. | Click Post. |
| 3. | Click OK. |
|   |
Note: If required, you can also post and close progress bills in batch. |
| 4. | Close the page. |
| 5. | Go to Default dashboard. |
If you claimed the revenue temporarily, you can only post and close a progress bill if the posted revenue is reversed.
| Related to | Notes |
|---|---|
|
Use progress billing without temporary revenue claim |
  |
|
Use progress billing with temporary revenue claim |
  |