If you have defined a cost code standard and cost code level for a project quotation, you can define a cost code for each WBS line. If the cost code level is Transaction, you can also define a cost code for each estimated-costs-and-revenue line. So, estimated-costs-and-revenue lines of one WBS line can have different cost codes.
1. | Click Advanced project management. |
2. | Click Project quotation. |
3. | In the list, click the link in the selected row. |
4. | Click Advanced WBS. |
5. | Click Edit. |
6. | Select a task having estimate lines. |
7. | Click the Estimated costs and revenues tab. |
8. | In the list, find and select the desired record. |
9. | In the Cost code field, enter or select a value. |
  |
Note: You can only change the cost code on an estimate line if the default cost code level is set to Transaction. |
Related to | Notes |
---|---|
Use cost codes in work breakdown structure |
  |