If you use retention terms that are based on an invoiced amounts schedule, set up the progress amount retention terms.
Example
Retention schedule:
Amount from | Amount to | Retention percentage |
---|---|---|
0 | 500,000 | 8 |
500,000 | 800,000 | 6 |
800,000 | 9,999,999 | 4 |
Retention calculation:
Progress bill amount | Total claimed amount* | Retention calculation | Retention | |
---|---|---|---|---|
1 | 400,000 | 0 | 400,000 x 8% | 32,000 |
2 | 200,000 | 400,000 | (100,000 x 8%) + (100,000 x 6%) | 14,000 |
3 | 100,000 | 600,000 | 100,000 x 6% | 6,000 |
4 | 300,000 | 700,000 | (100,000 X 6%) + (200,000 x 4%) | 14,000 |
*Total claimed mount = The sum of the previous progress bill amounts. |
1. | Click Project management and accounting -> Setup -> Retention -> Progress amount retention terms. |
2. | Click New and enter a description. |
3. | On the Schedule pane, click Add line and fill in the fields. |
  |
Note: You only can fill in the Amount to and the Percent to retain. The Amount from is automatically determined based on the highest entered To amount. |