Cost codes (or job codes) can be defined in the system to represent an internal or external code which is used to represent a fixed activity or cost category.
Cost codes can be entered manually or can be imported using the standard Microsoft Dynamics AX tools or the Business Integration Solution (BIS).
• Cost code can be based on an external standard or list.
• Cost code can also represent an internal code which is used for reporting and analysis.
• Cost code must be linked to a cost code standard. The combination of cost code and cost code standard is unique.
| 1. | Go to Project management and accounting > Setup > Advanced project management > Cost code setup > Cost codes. | 
| 2. | Click Cost codes. | 
| 3. | Click New. | 
| 4. | In the Cost code field, type a value. | 
| 5. | In the Description field, type a value. | 
| 6. | In the Cost code standard field, enter or select a value. | 
| 7. | In the Cost code group field, enter or select a value. | 
| 8. | Close the page. | 
| Related to | Notes | 
|---|---|
| Set up cost codes |   |