If a data quality policy is checked out in another environment, you can take over the check-out in the current environment. Only do this if the policy cannot be checked in from the other environment.
When you take over the data quality policy:
It is blocked for changes in the other environment.
Any changes made in the other environment are undone.
It is checked out in the current environment.
It receives a provisional change set number in the current environment that is two higher than the latest change set.
For example: If the latest change set is 4, the policy gets provisional change set number 5 when checked out in another environment. If you take over the policy in the current environment, it gets provisional change set number 6.
Steps
Go to Data quality studio > Inquiries > Version management > Data quality policy version management.
In the list, find and select the desired data quality policy.
Click Steal check out.
You can choose to continue taking over the check-out of the selected data quality policy or cancel the action.
Click Yes.
Close the page.