- Data Management
- RapidValue
- Activities
If you have set up an integration between a RapidValue solution and an Azure DevOps project, you can synchronize the data between these two. With this integration you can synchronize RapidValue entities with DevOps work items in both directions. The data is synchronized according to the DevOps mapping setup.
This topic explains how to synchronize a selected business process.
If you synchronize a selected business process, this is done:
- The selected business process is synchronized. If the business process is not mapped to a work item, a work item is created and mapped to the business process.
- Its parent business processes, all the way up to the top node in the business process hierarchy, are checked. If a parent business process is not mapped to a work item, a work item is created and mapped to the parent business process. Already mapped parent business processes are not synchronized.
Note: If you use work packages, the mapped work item gets the work package work item as the parent. And the work package work item gets the work package group work item as parent. If the work package group or work package is not mapped to a work item, a work item is created and mapped to the work package group or work package.
- All its child business processes are synchronized, all the way to the lowest nodes in the underlying business process hierarchy.
Note: If you use work packages, also for the child business processes, the mapped work item gets the work package work item as the parent. And the work package work item gets the work package group work item as parent.
- The requirements that are assigned to the synchronized business processes are synchronized. Also, the child requirements of these requirements are synchronized. If a requirement is not mapped to a work item, a work item is created and mapped to the requirement.
Note: Only the business processes are mapped that meet the relevant mapping conditions.
Standard procedure
1. |
Click Business process modeling. |
2. |
Click the Business processes tab. |
3. |
In the tree, select 'a business process'. |
4. |
Click DevOps. |
5. |
Click Synchronize. |
See also