Before you record a scenario or a process flow, usually, you first assign a procedure activity to the relevant business process.
1. | Click Business process modeling. |
2. | Click the Business processes tab. |
3. | Click Edit hierarchy. |
4. | In the tree, select 'a node'. |
5. | Click the Procedure tab. |
6. | Click Assign. |
7. | On the Existing tab, in the list, find and select the activity that you want to copy. |
8. | Click the Copy tab. |
9. | In the Activity field, change the default activity name. |
10. | In the Role field, enter or select a value. |
11. | In the Area field, enter or select a value. |
12. | The default type is Scenario. |
  | In the Type field, you can select another type. |
13. | Click OK. |
Related to | Notes |
---|---|
Assign procedure activity |
  |
Assign procedure activity |
  |