Pre-process activities represent activities that must be performed before production and are generated for released production order components. Register pre-process activities as each activity is completed. For more information on pre-process activities, see Pre-process activities.
Steps
In the search box, enter Pre-Process Activities, and then choose the related link.
Open the relevant pre-process activity.
Enter the quantity of the specified production component you want to process (and a lot number if necessary) on the activity lines. If you are processing several item lots, enter a different lot on each line.
Depending on setup, posting an associated blending order may automatically populate the pre-process activity lines with the necessary information.
On the Actions tab, in the Functions group, choose Register.
Choose Yes. The activity lines are registered.
Registering a pre-process activity instructs the program to move the item on the activity lines from the pre-process inbound bin to the outbound bin. The pre-process activity remains open if there is an additional quantity to process.